Previous Page  42 / 100 Next Page
Information
Show Menu
Previous Page 42 / 100 Next Page
Page Background

ALLU,

FINLAND

R

ecent developments and growing environmental

awareness have seen increasing numbers of pipeline

contractors taking advantage of some of the latest

technology on the market. In many cases the

contractors have utilised ALLU Transformer screeners and

screener-crushers to provide bedding and to cover the freshly

lowered pipe with fine soil. The soil used is the excavated

material from the pipelaying, with the impurities and rocks, etc.

being processed out, thereby ‘transforming’ it into fine soil ideal

for the filling in of the trench.

The ALLU Transformers are attached to the pipeliners’

excavators in place of the factory supplied bucket. They operate

hydraulically from the excavator’s own hydraulics in order to

separate soil from rock and debris. In doing this, several hundred

m

3

/d of soil spoils per excavator are able to be processed, as

they move along the pipeline track where the freshly laid pipe is

waiting to be covered with up to 600 mm of finely screened or

crushed soil. This soil is required to be laid underneath, around,

and on top of the pipe in the trench to prevent stones and

foreign debris from scratching or etching the pipe underground.

This could lead to leaking of any liquid being transported. This

helps to make the pipelaying process more efficient, and also

ensures that it is as environmentally friendly as possible, by

reusing excavated materials, and ensuring the pipe does not

contaminate the surrounding area.

In addition, there is no need for the contractors to

spend large amounts on buying in sand or top soil. As well

as sand being a valuable commodity, it is also becoming an

increasingly endangered naturally occurring material. If soil is

able to be reused in-situ, the

environmental benefits are

significant. It also means there is

no need to transport material from

large distances, which can endanger

workers and the environment alike.

The stones and rocks being excavated

from the trench are also an ideal source

of sub-base and aggregate.

Some contractors have been using the

combination of an ALLU D-Series Transformer

with TS®drum. Designed to be mounted on

12 t loaders, and 8 t tractors and backhoe loaders,

the ALLU Transformer D-Series is comprised of a

mounted attachment which screens, crushes, aerates,

blends, mixes, separates, feeds, and loads materials.

This results in the feed material being transformed into

valuable products.

The use of the fine-screening ALLU TS drum

construction when fitted with standard blades enables

material to be screened on-site, and then backfilled directly

into a trench. At the core of the TS drum construction is the

configuration of the screening blades that spin between the

screening combs. The end product size is defined by the space

between the combs, and different fragment sizes can be achieved

by repositioning the blades. As the screening combs carry most

of the material weight, the drums and bearings experience less

impact and load, with the design of the assembly ensuring the

machine works well in wet and dry materials without clogging.

In one recent example a major pipeline contractor

achieved savings in excess of 80% per m

3

using an ALLU

Transformer D-Series attachment with TS drum assembly –

specifically a DH 3-12 TS16 – fitted to a standard excavator.

The US based contractor found that traditional screening

provided low productivity and proved inefficient, as

large soil particles and stones were often getting into

the trench. The traditional option in this situation

available to pipelaying contractors has been to

buy in soil or sand. However, the high cost of

soil made this an unattractive option. After

switching to an ALLU Transformer with TS

drum construction, the contractor found

that they were achieving high rates of

productivity and their costs were

significantly lower.

TS blades are available in two

different types: standard blades

for screening applications, and

axe blades when a crushing or

shredding effect is required.

Blade sizes that are available

include 16 - 32 mm,

25 - 50 mm and 35 mm.

ALLU D series at pipeline jobsite.

ALLU D series working at pipeline jobsite in Ireland.

Heavy equipment review

40